01 / 04 Net Zero Building

Net zero, priced and sequenced.

We assess your building, price every upgrade as an investment and sequence the work around equipment life and your capital plans. Then we measure whether the savings arrive.

Axonometric drawing of a typical ten-storey office buildingThree findings are marked in orange: the 1994 rooftop units, lighting left on in empty areas, and building controls whose schedules no longer match occupancy. +38.00±0.00−4.20 Rooftop units, 1994Gas-fired, near end of life 1 Lighting on 15 h a dayIncluding empty floors 2 Controls out of stepSchedules no longer match use 3

Typical building · modelled

  1. Rooftop units, 1994. Gas-fired and near the end of their life.
  2. Lighting on 15 hours a day. Including on empty floors.
  3. Controls out of step. Schedules no longer match occupancy.

What we do

Every building holds a list of decisions: what to replace, what to upgrade, when, and how to pay for it. Neutra turns that list into an investment plan you can defend — engineered, priced and measured.

01 Approach

Assess. Plan.
Deliver. Monitor.

One continuous process, so the numbers that justify an upgrade are the same numbers it is measured against.

  1. 01 / 04

    Assess

    AI-assisted building assessments and virtual energy audits establish where energy, money and emissions go, and where the opportunities are.

    • Energy and emissions baseline
    • End-use breakdown
    • Benchmark against national medians
    • Shortlist of opportunities
    BASELINE ENERGY USE, MWh/yr3.2 GWh Space heating1,900Lighting485Plug loads465Cooling160Water heating95Fans and pumps95 Opportunity identified
    The typical building modelled below.
  2. 02 / 04

    Plan

    Every upgrade is costed and modelled for capital cost, savings, payback, net present value and emissions, then sequenced around equipment life and your capital plans.

    • Costed, ranked upgrades
    • Payback and net present value
    • Cost per tonne avoided
    • Sequenced capital plan
    PHASED PLAN, CUMULATIVE CASH FLOW +$0.4M$0−$0.4M Break-even, year 14 +$402k Year 05101520
    The typical building modelled below, before incentives.
  3. 03 / 04

    Deliver

    We connect the plan to incentives, financing options and vetted implementation partners, phase by phase.

    • Incentives and tax credits
    • Financing options
    • Vetted implementation partners
    PHASING, CAPITAL BY YEAR$870k Y1Y2Y3Y4Y5 01 Controls$80k02 Lighting$330k03 Ventilation$70k04 Heat pumps$260k05 Solar$130k Financing and partners for each phase
    The typical building modelled below.
  4. 04 / 04

    Monitor

    Ongoing performance monitoring and fault detection compare the building with its plan, so savings don’t quietly erode.

    • Performance against plan
    • Fault detection
    • Data for annual reporting
    ACTUAL VS EXPECTED, DAILY ELECTRICITY Alert, day 29: damper stuck open Day 1Day 42 Expected range
    An example fault, not a real alert.

02 Typical building

Explore a building.

A typical 1988 ten-storey office in Toronto, modelled from Canadian benchmarks and 2026 energy prices. Choose an upgrade to see the assessment, the recommendation, the investment case, the emissions impact and what we would monitor.

Typical building · modelled · not a client project

Axonometric drawing of the typical office buildingThe selected upgrade is highlighted in orange on the drawing; details appear alongside. +38.00±0.00−4.20 01 02 03 04 05

01 Building automation · Year 1

Recommission the building automation system

Assessment
Heating and cooling run 16 hours a day, six days a week; the building is occupied about 10 hours, five days. Floors 3–6 heat and cool at the same time.
Recommended upgrade
Reset schedules and setpoints, add supply-air temperature reset and repair the economizer dampers.Berkeley Lab’s study of commissioning in existing buildings found median whole-building savings of 16%. This model assumes 9%.
Investment

$80,000Capital cost

$17,840Savings a year

4.5 yrsSimple payback

+$125,000Net present value

Emissions

−45 tCO₂e a year, 10% of the building’s total

Monitoring

Schedule adherence, simultaneous heating and cooling, economizer position.

Hours run outside schedule · 28 days

Example alert: weekend override left on

02 Lighting · Year 1

LED lighting with occupancy and daylight control

Assessment
T8 fluorescent fixtures on every floor stay on in empty areas until cleaning ends at 10 pm. Lighting is about 15% of the building’s energy.
Recommended upgrade
LED retrofit with networked occupancy and daylight sensors, zoned by floor.Net of the extra winter heating that cooler LED lighting causes. A Berkeley Lab meta-analysis found lighting controls alone save 24–38% of lighting energy on average.
Investment

$330,000Capital cost

$47,400Savings a year

7.0 yrsSimple payback

+$214,000Net present value

Emissions

−18 tCO₂e a year, 4% of the building’s total

Monitoring

Lighting power by floor and after-hours load.

After-hours lighting, kW · 28 days

Example alert: floor 7 sensors offline, lights held on

03 Ventilation · Year 2

Demand-controlled ventilation

Assessment
Outdoor-air dampers are fixed for full design occupancy all day. Badge data shows floors are, on average, about half full, and all of that air is heated or cooled.
Recommended upgrade
CO₂ sensors on every floor reset the outdoor-air dampers on both rooftop units to match actual occupancy.With natural gas at about 25¢/m³, most of the value is in carbon rather than cost.
Investment

$70,000Capital cost

$6,240Savings a year

11.2 yrsSimple payback

+$1,000Net present value

Emissions

−31 tCO₂e a year, 7% of the building’s total

Monitoring

Zone CO₂ against setpoint and outdoor-air fraction.

Peak CO₂ on floor 4, ppm · 28 days

Example alert: floor 4 CO₂ sensor reading flat

04 Heating and cooling · Year 4

Heat pump rooftop units, at end of life

Assessment
Two gas-fired rooftop units from 1994 are near the end of their service life. After upgrades 01–03 they still burn about half of the building’s gas.
Recommended upgrade
Replace them at end of life with cold-climate heat pump units, integrated with the automation system. The perimeter boilers stay for now.Replacement is due either way, at about $400,000 like-for-like, so the cost shown is the premium. At 2026 Ontario prices heat from a heat pump costs more than heat from gas: this upgrade raises energy costs while cutting the most carbon. Owners who can claim the federal 30% Clean Technology ITC would recover about $198,000.
Investment

$260,000Heat pump premium

−$17,920Savings a year

NoneCosts more to run

−$391,000Net present value

Emissions

−127 tCO₂e a year, 28% of the building’s total

Monitoring

Coefficient of performance, defrost cycles, backup heat use.

Coefficient of performance · 28 days

Example alert: efficiency below 2.0, defrost cycling

05 On-site generation · Year 5

Rooftop solar array

Assessment
About 260 m² of clear roof remains once the rooftop units are replaced.
Recommended upgrade
A 52 kW array sized to the clear roof area, producing about 60 MWh a year.On Ontario’s low-carbon grid, solar saves money slowly and cuts little carbon. It comes last. Owners who can claim the federal 30% Clean Technology ITC would recover about $39,000.
Investment

$130,000Capital cost

$9,600Savings a year

13.5 yrsSimple payback

−$16,000Net present value

Emissions

−4 tCO₂e a year, 1% of the building’s total

Monitoring

Generation against weather-adjusted expectation; inverter status.

Daily generation, kWh · 28 days

Example alert: one string offline, output 40% below expected

All Combined plan · Years 1–5

Five upgrades, sequenced and priced as one investment

$870,000Capital cost

$63,160Savings a year

13.8 yrsSimple payback

−$67,000Net present value

−225 tCO₂e a year, −50%

−25%Energy cost

Net cost per tonne of CO₂e avoided

Saves moneyCosts moneyBar width: tonnes avoided a year

Upgrades 01 and 02 carry the plan’s value, and 03 roughly breaks even. Upgrade 04 delivers 57% of the carbon cut but raises energy costs at 2026 prices. If the owner can claim the federal 30% Clean Technology ITC on the heat pumps and solar, net present value becomes about +$130,000.

  1. Year 101 Controls, 02 Lighting
  2. Year 203 Ventilation
  3. Year 404 Heat pumps, at end of life
  4. Year 505 Solar
Project
Typical office, Toronto (modelled)
Type
Mid-rise office, 10 storeys, built 1988
Floor area
12,400 m² · 133,500 ft²
Baseline a year
3.2 GWh · $254,000 · 448 tCO₂e
Sheet
D-01

A modelled example of a typical building, not a client project, a forecast or a quote. Its energy use follows the end-use pattern NRCan reports for Ontario office buildings, at 0.93 GJ/m² — between the Canadian median for offices (0.87 GJ/m²) and the Ontario average for office buildings (1.27 GJ/m²). Electricity at $0.16/kWh; natural gas at about 25¢/m³ ($0.024/kWh), with no federal fuel charge. Emission factors: 0.074 kgCO₂e/kWh for Ontario’s grid in 2024 and 0.185 kgCO₂e/kWh for natural gas. Upgrades are modelled in sequence, so each shows savings after the ones before it. Net present value uses a 20-year life and a 6% real discount rate, before incentives. Monitoring charts show example patterns. Figures are rounded; sources are listed below.

03 Net zero

What net zero asks of a building.

In Canada, the Canada Green Building Council’s Zero Carbon Building – Performance Standard defines net zero for existing buildings, with verification every year. We plan in the order that costs least per tonne.

  1. 1

    Use less

    Controls, lighting, ventilation and envelope repairs come first. They cost least per tonne and shrink every system that follows.

  2. 2

    Electrify heat

    Replace combustion equipment with heat pumps at the end of its life, sized for the smaller load.

  3. 3

    Generate and buy clean

    Add on-site renewables where the roof allows, and procure clean electricity for the rest.

  4. 4

    Balance the rest

    Under the CaGBC standard, what remains, including embodied carbon and refrigerant leaks, is balanced with renewable energy certificates or carbon offsets.

The Zero Carbon Building – Performance Standard asks you to

  • Reach a zero carbon balance every year
  • Offset embodied carbon and any refrigerant leaks
  • Report energy use intensity and seasonal peak demand
  • Keep a transition plan for on-site combustion, updated every five years
  • Show proof of renewable energy certificates and offsets

The typical building, after its five-year plan

The five-year plan cuts the building’s emissions by 50%, from 448 to 223 tCO₂e a year. What remains is mostly the gas-fired perimeter boilers and domestic hot water — the next end-of-life decision — plus the grid electricity the building still buys.

04 Requirements

Rules your building may already face.

Large-building reporting is already law in Ontario, Toronto and Montréal, and Vancouver now limits emissions. We set up the reporting and plan against the limits.

Status as of November 2026

JurisdictionApplies toWhat it requires
OntarioO. Reg. 506/18, energy and water reportingBuildings of 50,000 ft² and largerReport energy and water use to the province every year by July 1, through ENERGY STAR Portfolio Manager.
TorontoMunicipal Code, Chapter 367Buildings of 50,000 ft² and larger; buildings from 10,000 ft² are being phased inReport energy and water use to the City every year. The City describes the by-law as the basis for future performance standards.
MontréalBy-law 21-042Buildings of 2,000 m² or more, or with 25 or more dwellingsReport energy use and greenhouse gas emissions every year by June 30; buildings receive a GHG performance rating.
VancouverAnnual GHG and Energy Limits By-lawOffices and retail of 100,000 ft² and largerAnnual emissions limits from 2026: 25 kgCO₂e/m² for offices and 14 for retail, falling to zero by 2040. Emissions from electricity do not count toward the limit.

If this typical building stood in Vancouver, its gas emissions — about 28 kgCO₂e/m² — would exceed the 2026 limit for large offices. After the five-year plan, they would be about 12 kgCO₂e/m².

05 Paying for it

Make every phase fundable.

  • Clean Technology ITC

    A refundable federal tax credit of 30% on eligible heat pumps, solar and other clean technology, available to taxable Canadian corporations and REITs.

  • Utility incentives

    Ontario’s Save on Energy and Enbridge Gas run incentive programs for efficiency upgrades. We check what applies to each measure before you commit.

  • Financing and partners

    Each phase is matched to financing options and vetted implementation partners, so the plan is executable, not just approved.

Sources

  1. Natural Resources Canada, Canadian Energy Use Intensity by Property Type, ENERGY STAR Portfolio Manager technical reference, August 2023. Office median site EUI 0.87 GJ/m².
  2. Natural Resources Canada, Comprehensive Energy Use Database, Ontario, offices: energy use by end use, 2023 data.
  3. The Atmospheric Fund, Carbon Emissions Inventory: electricity grid, 2024 data. Ontario grid intensity 73.8 gCO₂e/kWh.
  4. Environment and Climate Change Canada, Emission factors and reference values: natural gas, Ontario.
  5. Ontario Energy Board, Natural gas rates, Enbridge Gas, effective October 1, 2026: gas supply 9.1¢/m³, transportation 5.5¢/m³, federal carbon charge 0¢/m³.
  6. Hydro-Québec, Comparison of Electricity Prices in Major North American Cities, rates in effect April 1, 2023: Toronto medium-power customers 14.6–18.1¢/kWh before tax.
  7. E. Mills, Building Commissioning: A Golden Opportunity for Reducing Energy Costs and Greenhouse Gas Emissions, Lawrence Berkeley National Laboratory, 2009.
  8. A. Williams et al., Lighting Controls in Commercial Buildings, LEUKOS, 2012.
  9. Toronto and Region Conservation Authority, Sustainable Technologies Evaluation Program, comparison of rooftop solar sites in the Greater Toronto Area.
  10. Canada Green Building Council, Zero Carbon Building Standards.
  11. Government of Ontario, Report energy and water use for large buildings; City of Toronto, energy and water reporting and benchmarking; Ville de Montréal, By-law concerning GHG emission disclosures and ratings of large buildings; City of Vancouver, Annual GHG and Energy Limits By-law FAQ.
  12. Fasken, Canada’s clean energy investment tax credits, October 2024.

06 Contact

Discuss your building.

Tell us about a building or a portfolio: what it is, where it is and what you want from it. We’ll reply to arrange a conversation.

Or outline your needs here

What matters most

Opens your email app with these details filled in. Nothing is sent until you press send.

Discuss your building